cost clear a lot, nanawale?
#2
Before bulldozing, get a septic system contractor to draw up the plans for the best location for the excavation. Next, a civil engineer can tell you how much fill is needed for the house foundation (post and pier) and driveway. Then, lay down and rest because the price will be a nightmare. Check with the homeowner's association too, because the CC&R's will introduce complications, albeit not as severe as DPP.
If you are leveling the area to build a farm, you still might want to plan for a four sided fence, and that would take a survey, to avoid future lawsuits.