From Roy Takemoto who is the executive assistant to Mayor Kim:
UPPER SECTION OF HIGHWAY 132:
Road striping and installation of signage on the upper portion of Highway 132... is expected to begin next month, with that section of the road anticipated to be open by Thanksgiving.
LOWER PART OF HIGHWAY 132:
The lower section of the road is still too hot to drive on, but paving is complete and about 30 percent of the shoulder work is done.
https://www.westhawaiitoday.com/2019/10/...oing-well/
UPPER SECTION OF HIGHWAY 132:
Road striping and installation of signage on the upper portion of Highway 132... is expected to begin next month, with that section of the road anticipated to be open by Thanksgiving.
LOWER PART OF HIGHWAY 132:
The lower section of the road is still too hot to drive on, but paving is complete and about 30 percent of the shoulder work is done.
https://www.westhawaiitoday.com/2019/10/...oing-well/