See HCC chapter 10: erosion and sedementation control.
No grading/grubbing work without a permit, there are exceptions but likely none of them apply here. No stockpiling without a stockpiling permit. Grading more than 15000 square feet requires contour map prepared by engineer/surveyor. Cut or fill greater than 15 feet in height requires a soils report. Additional requirements apply when close to a property line. Payment of fees required for permit. Only available where rule of law applies.
a new open-sided workshop
Larger than 600 square feet?
No grading/grubbing work without a permit, there are exceptions but likely none of them apply here. No stockpiling without a stockpiling permit. Grading more than 15000 square feet requires contour map prepared by engineer/surveyor. Cut or fill greater than 15 feet in height requires a soils report. Additional requirements apply when close to a property line. Payment of fees required for permit. Only available where rule of law applies.
a new open-sided workshop
Larger than 600 square feet?