Today was a big day for us, Christmas come early. We have been building in HPP and passed the final inspection on the garage, the framing inspection passed on the main house and a couple of exterior plumbing changes were approved. The ohana has a couple of very minor deficiencies that we expect to have resolved right away. This has come in the nick of time as we are arriving on the BI for an extended stay on Tuesday! Another milestone will be when Jerry moves us from temporary to permanent power. There are so many who have worked to help us with building long-distance, but specific thanks due to the core team of: Daniel Bona (design) and Cat and Robert Emery(and crew); and then MSW Electric; MK Plumbing; Dave Darrah (framing); Kene (rock artistry); Jason(drywall); Steve and Cindy (painters); Ian Rozett(landscaping).