Posts: 4,903
Threads: 83
Joined: Feb 2009
Why not just designate highway 130 as the PMAR and build an entirely
new 4 lane limited access highway ?
It would be far cheaper and a lot quicker.
Highway 130 is so flawed because of the hundreds of driveways that the county has allowed, that it will cost millions more to make it workable.
Another solution would be a complete building moratorium in lower Puna until a solution is in place !!
Posts: 148
Threads: 9
Joined: Apr 2009
I wonder if they looked at 40 or 41st street thru Orchidland and Ainaloa as a paralel route to 130?Also If they Extend the turn pocket From 11 to 130 to hold more traffic in que , the light will control the Flow southbound to Puna with the sensors. They need to extend the light phase going south too. Maybe even K rail the lanes so there is no three lanes into two but two lanes south and two lanes turninG to the school. Just a couple of low cost ideas.
Posts: 1,581
Threads: 26
Joined: Jun 2007
quote:
Originally posted by punaticbychoice
Procurement reform and contract administration.
Understand everyone?
I'm sure everyone knows it's needed. BUT, government contracting and procurement is not designed to save money. The whole process, much in place to ensure fairness, cost money. There is really no way to save any meaningful money because what the people want can not be done in a cost savings manner. It's just common sense.
Posts: 2,899
Threads: 489
Joined: Mar 2006
So from what I gather here...The answer to hotinhawaii's question is.... with regard to:
STP28 (Humane Society to Shower Drive widening)...."Tentatively" to start October 2012
And from Shower Drive to Hwy 137 STP27.....To start 2017
As per:
http://ow.ly/4HQ74
I'm kinda wondering if I'll still be alive when it's all completed!
Posts: 1,175
Threads: 12
Joined: Jun 2008
Bob, it's good to know that you recognize government has a different function than private for profit business.