My understanding that the soil under post & peer is not required to be treated with poison for termites .Does anyone know if it's mandatory to treat under post & peer if there is concrete under?
The P&P is 5.6 ft if it matters.
I'd appreciate the information.
___________________________
Whatever you assume,please
just ask a question first.
Posts: 8,470
Threads: 1,033
Joined: May 2003
It's my understanding that treatment is required. Best to check with Building and Safety: 961-8331
Punaweb moderator
Assume the best and ask questions.
Punaweb moderator
Posts: 2,019
Threads: 201
Joined: Jan 2008
Thanks,Rob.
___________________________
Whatever you assume,please
just ask a question first.
Posts: 2,189
Threads: 295
Joined: Sep 2004
Treatment is definitely required. When we built, we had it done and had to have certification signed by the company that did it. This was given to the building inspector in the check-off process.
I want to be the kind of woman that, when my feet
hit the floor each morning, the devil says
"Oh Crap, She's up!"
Posts: 2,019
Threads: 201
Joined: Jan 2008
Thank you,Pam.Do you remember what chemical was used ?
Just wondering if there are options to choose from.