Grace Pacific should start paving the Saddle Road 6(7) phase next week, if the CFLHD approves their asphalt mix design. They were supposed to start work in early April, but were waiting for a EPA permit.
Goodfellow has completed the abutments for the GRS-IBS overpass. They're working on the support posts and should start constructing the deck soon.
The overall project is going well-except for the utility relocation by m.m 41.67. HELCO and the HDOT haven't executed the utility relocation agreement yet.
Goodfellow has completed the abutments for the GRS-IBS overpass. They're working on the support posts and should start constructing the deck soon.
The overall project is going well-except for the utility relocation by m.m 41.67. HELCO and the HDOT haven't executed the utility relocation agreement yet.