pouring piers into forms
#1
Aloha,

When pouring piers into forms on a solid rock slab, before pouring...

how deep would you want to drill, to anchor the rebar into the rock?

I was thinking ~1 ft.

would that be sufficient? do I need to sink it in deeper? would 1 ft be overkill?

Mahalo
Reply


Messages In This Thread
pouring piers into forms - by rainyjim - 02-27-2014, 06:11 AM
RE: pouring piers into forms - by Rob Tucker - 02-27-2014, 06:21 AM
RE: pouring piers into forms - by rainyjim - 02-27-2014, 07:26 AM
RE: pouring piers into forms - by Seeb - 02-27-2014, 08:00 AM
RE: pouring piers into forms - by kalakoa - 02-27-2014, 09:39 AM
RE: pouring piers into forms - by DanielP - 02-27-2014, 12:03 PM
RE: pouring piers into forms - by unknownjulie - 02-28-2014, 04:43 PM
RE: pouring piers into forms - by DanielP - 03-01-2014, 06:25 AM
RE: pouring piers into forms - by Seeb - 03-09-2014, 06:22 AM