In July, the P&R had noted that compliance repairs would take a minimum of 120 days (working days) and that any additional work could run over...in August Jason picked that up in a Trib Herald article, but only stated up to 120 days...nothing about the working part...have no idea if that was from the press release or interpretation of 120 days... but it would have been easy for the stress on working to get lost...and eventually filter down to someone interpreting 120 days to equal 3-4 months...
The delay from fall to winter was due to the initial bid not including some important things, and having to rebid the contract & getting a new contractor...
The delay from fall to winter was due to the initial bid not including some important things, and having to rebid the contract & getting a new contractor...