The utility relocation agreement was almost executed, but the State Attorney General's office made a slight change to the agreement language, which required the CFLHD to review the agreement again. They resubmitted it back to the State AG's office and HDOT. HDOT is reviewing the agreement again.
The project is supposed to be completed by September, so the clock is ticking to complete the relocation and construct the 3,700 feet of new roadway in this area.