02-01-2006, 08:16 AM
for the specs on the temp pole - go to the Helco engineering office - at 54 Halekauila St.
As for power, you actually do not have to have a permit for temp power - HELCO will put in temp power for 1 year. HELCO does try to deter this with obstacles, but if your permit isnt ready yet, you may still get power - the cost is just higher.