The last set of electrical permits I filed for came back in 7 days. A month was the average for the past year.

So maybe with the boom history the permitting process will speed up. Or maybe it was just a fluke.

Jerry
Art and Orchids B&B
http://www.artandorchids.com
Jerry
Art and Orchids B&B
http://www.artandorchids.com
Reply


Messages In This Thread
Permit /Building Questions - by doscabos - 11-07-2007, 12:39 PM
RE: Permit /Building Questions - by John S. Rabi - 11-07-2007, 01:29 PM
RE: Permit /Building Questions - by Rob Tucker - 11-07-2007, 04:53 PM
RE: Permit /Building Questions - by John S. Rabi - 11-07-2007, 05:54 PM
RE: Permit /Building Questions - by Kapohocat - 11-08-2007, 07:15 AM
RE: Permit /Building Questions - by missydog1 - 11-08-2007, 09:24 AM
RE: Permit /Building Questions - by Kapohocat - 11-08-2007, 09:41 AM
RE: Permit /Building Questions - by John S. Rabi - 11-08-2007, 09:52 AM
RE: Permit /Building Questions - by Kapohocat - 11-08-2007, 10:45 AM
RE: Permit /Building Questions - by Kapohocat - 11-08-2007, 10:52 AM
RE: Permit /Building Questions - by janeadams - 11-08-2007, 11:40 AM
RE: Permit /Building Questions - by Kapohocat - 11-08-2007, 12:45 PM
RE: Permit /Building Questions - by jerry - 11-10-2007, 12:03 PM
RE: Permit /Building Questions - by Kapohocat - 11-10-2007, 02:35 PM
RE: Permit /Building Questions - by Carey - 11-10-2007, 03:09 PM
RE: Permit /Building Questions - by Carey - 11-10-2007, 04:57 PM
RE: Permit /Building Questions - by Kapohocat - 11-11-2007, 04:01 AM

Forum Jump:


Users browsing this thread: 3 Guest(s)