Thanks for posting all the links.
I did look at read both the HTH article Moderator 2 posted as well as the link Obie posted that is direct to the County website, and notwithstanding all that, and I admit have NOT watched the several update videos that run about an hour plus each and nowhere do I find anything that comes close to being describable as:
"As was reported last month, the most recent snafu -- generally blamed on the surveyors the County hired -- ended up costing taxpayers a bit under a million dollars and slowed the project down by four months. With that kind of motivation the contractor shouldn't have any trouble finding something else to jack up the price again."
In fact, the only reference I can find that comes close mentions in the November update that "The initial investigation identified potential discrepancies in the ground surface elevations," along with "we are currently working to resolve these discrepancies before moving forward with construction."
Further, the January update states: "Identified issues with existing grades have been resolved."
I see no mention of close to a million dollar change order, and again, while I am not saying that it may not be real, I am saying I see no verifiable reporting of this delay and change.
The HTH article says this:
- This progress is despite complications discovered by contractor Isemoto Contracting Co.
- Public Works Project Manager Alex Kalawe said a preliminary site investigation found a discrepancy between plans drawn up for the project and the reality of the site.
- While Kalawe did not go into detail about the nature of the discrepancy, he said he believes it should be resolved within a month, and any impacts on the timeline will be determined depending on that resolution.
However, having said that, and if true, how can the contractor be blamed for seeking additional compensation for doing additional work?
I highly doubt Rob's construction enterprises would bid a job based on known and stated assumptions at the time the project is bid and not seeking additional monies when the site conditions are considerably different when the actual work is performed.
And I doubt he would do the work without a change order in hand PRIOR to doing the work.
At any event, it's a monumental project that's for sure!