Some interesting info for HPP residents concerned with the current paving of roads in the Park.....
7th avenue "paving" was completed Monday 10/20/08 between Makuu and Paradise. The actual paving took only one day for a mile of road. The prep work took two weeks!
So far since paving started in March...HPP has had 22nd (from Makuu to Shower), K, E, L, part of 7th street(from Makuu to Paradise) and 33rd from Makuu towards Paradise (dead end) completed.
With the average paving price per mile at $280,000...HPP has spent approx. $1,880,000. to date of the 10 million borrowed.
With more than half of Phase 1 finished, completion should be some time in April of 2009 with the paving of 7th (from Paradise to Kaloli), 16th (from Makuu to Kaloli) and 1st (from Makuu to Paradise).
HPP Resident Paving watchdog.
7th avenue "paving" was completed Monday 10/20/08 between Makuu and Paradise. The actual paving took only one day for a mile of road. The prep work took two weeks!
So far since paving started in March...HPP has had 22nd (from Makuu to Shower), K, E, L, part of 7th street(from Makuu to Paradise) and 33rd from Makuu towards Paradise (dead end) completed.
With the average paving price per mile at $280,000...HPP has spent approx. $1,880,000. to date of the 10 million borrowed.
With more than half of Phase 1 finished, completion should be some time in April of 2009 with the paving of 7th (from Paradise to Kaloli), 16th (from Makuu to Kaloli) and 1st (from Makuu to Paradise).
HPP Resident Paving watchdog.